[Call to Order] [00:00:05] FOR YOU TO ORDER, PLEASE. ALL RIGHT. WE'LL START OUT WITH 319, FOUND ON PAGES 35 OR 30 3 TO 35. [a. 2024-0319 – PUBLIC WORKS RE:     APPROVAL OF AN AMENDMENT TO AN ARCHITECTURAL/ENGINEERING CONSULTANT AGREEMENT BETWEEN ONEIDA COUNTY, THROUGH ITS DEPARTMENT OF PUBLIC WORKS, AND BARTON & LOGUIDICE, D.P.C.] PUBLIC WORKS SEEKS APPROVAL OF AN ARCHITECTURAL AND ENGINEERING AGREEMENT AMENDMENT WITH BARTON LOGIUDICE FOR THE MIDDLE SETTLEMENT ROAD RECONSTRUCTION PROJECT, NEW HARTFORD, THE CHANGES TO COVER AN ADDITIONAL EIGHT WEEKS OF CONSULTING SERVICES AND TO EXTEND CONSTRUCTION SUPPORT, INSPECTION AND CLOSEOUT SERVICES FOR THE PROJECT, THERE WAS AN ADDITIONAL 57,400, BRINGING THE TOTAL UP TO 373 500. ANY QUESTIONS FROM COMMITTEE SAID. YEAH, THIS PROJECT GOT DELAYED IN PART BECAUSE THE STATE WAS SLOWING APPROVING PROJECT DESIGN. IS THAT NOT RIGHT? I BELIEVE SO THIS IS PRIOR TO ME COMING ON, BUT I BELIEVE THAT WAS PART OF THE, THE ISSUE THERE. AND I THINK THERE WAS A LOT OF HANDS IN THE COOKIE JAR AS YOU SAY. YOU KNOW, FOR THAT TO YOU KNOW, A LOT OF PEOPLE HAD SAY IN THERE. SO SO EVERYBODY THAT HAD OVERSIGHT OUTSIDE OF THE STATE WAS PRETTY MUCH TREADING WATER TO MOVE ON. THIS AND, YOU KNOW, I JUST IT'S JUST UNFORTUNATE THAT A LOT OF PROJECTS WE SEE THERE'S ALWAYS ADDED COSTS AND THE FINAL YOU KNOW, THE WRAP UP OF THE SERVICES THAT THAT SHOULD HAVE BEEN ANTICIPATED TO. BUT I GUESS, YOU KNOW, YOU SEE OBVIOUSLY THIS IS A NEEDED EXPENSE. I MEAN, IT STARTED IN 2017. THE PROCESS OF FUNDING AND EVERYTHING ELSE. SO IT'S BEEN TOOK A LONG TIME. YEAH. AND THE DELAY COST THINGS LIKE, I REMEMBER RICK SHERMAN SAYING HE HAD TO, YOU KNOW, PAVE THAT PART OF THE, THE ROADWAY FOR WINTER AGAIN BECAUSE THE ROAD WASN'T READY TO GO. SO THERE WERE ADDED EXPENSES IN THAT RESPECT. BUT ANYWAY, YOU KNOW, IT'S JUST I UNDERSTAND THAT THESE THINGS GO ON. SO WELL. THANK YOU. YEAH. I'LL SET OTHER QUESTIONS. HAVING NONE. WE'LL CALL THE VOTE. ALL [b. 2024-0418 - PUBLIC WORKS RE:    APPROVAL OF A CONTRACT BETWEEN ONEIDA COUNTY, THROUGH ITS DEPARTMENT OF PUBLIC WORKS, AND CHA CONSULTING, INC.] IN FAVOR, SAY AYE. AYE. ANY OPPOSED? PASSES UNANIMOUSLY. MOVING ON TO 418. FOUND ON 36 TO 38IN COMMUNICATIONS. PUBLIC WORKS SEEKS APPROVAL OF A CONTRACT WITH CHC CONSULTING FOR DESIGN SERVICES, FOR THE CONVERSION OF INFIELD GRASS TO SYNTHETIC TURF WITH A COST OF $200,000. WE HAD TALKED ABOUT THIS BEFORE AND THIS IS JUST MOVING FORWARD WITH IT. ANY QUESTIONS FROM COMMITTEE HAVING NONE? WE'LL CALL THE VOTE. ALL IN FAVOR, SAY AYE. AYE. ANY [d. 2024-0485 - PLANNING RE:     ESTABLISHMENT OF CAPITAL PROJECT H – PLN – 136 – EXIT 31 TRAFFIC STUDY  ] OPPOSED? PASSES UNANIMOUSLY. MOVING ON TO 485 CAPITAL PROJECT CREATION ON PAGES 39 THROUGH 41, THE COUNTY EXECUTIVE REQUEST ESTABLISHMENT OF A CAPITAL PROJECT TO FUND THE THRUWAY EXIT 31 TRAFFIC SAFETY STUDY, WHICH WE'VE BEEN TALKING ABOUT FOR MONTHS, THAT PLANNING IS LOOKING AT. FEDERAL GOVERNMENT HAS COMMITTED $900,000 TO THE PROJECT, AND NO COUNTY DOLLARS ARE REQUIRED, THE STUDY IS PROJECTED FOR A 28 MONTH PERIOD. ANY QUESTIONS FROM COMMITTEE? HAVING NONE. WE'LL CALL THE VOT. ALL IN FAVOR, SAY AYE. AYE. ANY OPPOSED? PASSES UNANIMOUS. OKAY. [c. 2024-0515 – PUBLIC WORKS RE:    APPROVAL OF CHANGE ORDER NO. 2 TO AN AGREEMENT BETWEEN ONEIDA COUNTY, THROUGH ITS DEPARTMENT OF PUBLIC WORKS, AND FISHER ASSOCIATES, P.E., L.S., L.A., D.P.C.] MOVING ON TO 515, THIS IS A CHANGE. ORDER NUMBER TWO TO CONTRACT 17 2518 WITH FISHER ASSOCIATES TO PREPARE ENGINEERING DESIGN SERVICES FOR REPLACING VARIOUS STRUCTURES ON HOME AND CITY ROAD AND CHURCH ROAD IN THE TOWN OF PARIS, NEW YORK STATE. DEC IS REQUIRING THAT A WETLAND DELINEATION DELINEATION AND JUDICIAL JUDICIAL. JURISDICTIONAL. THERE YOU GO. JURISDICTIONAL. CAN'T EVEN SAY IT. CHAD THANK YOU. VERIFICATION BE PERFORMED, THE CHANGE ORDER WILL ADJUST THE SCOPE OF THE WORK AND INCREASE THE COST BY $11,000. QUESTIONS FROM COMMITTEE HAVING NONE. WE'LL CALL THE VOTE ALL IN FAVOR, SAY AYE. AYE. ANY OPPOSE? [e. 2024-0673 – PLANNING RE:  TRANSFER OF $104,266.00 TO A 9900 9901.900-000 – TRANSFER TO OTHER FUND (BUDGET)] [f. 2024-0672 – PLANNING RE: SUPPLEMENTAL APPROPRIATION OF $415,696.00 TO K 8221 8221.495-160 – OTHER EXPENSES GRANT FUNDED EXPENDITURES (PLANNING)] PASSES UNANIMOUSLY. AND WE HAD TWO DOWN THAT CAME DOWN LATE, 673 AND 672 ARE BOTH, BASICALLY THE SAME PROJECT, JUST TWO DIFFERENT, TWO DIFFERENT BREAKDOWN. THIS IS THE, THIS IS A RESOLUTION THAT WE PASSED, BACK IN AUGUST OF 2022, RESOLUTION 261, AUTHORIZING THE PLANNING DEPARTMENT TO APPLY FOR A GRANT FROM THE DEPARTMENT OF TRANSPORTATION FOR A SAFE STREETS AND ROADS FOR ALL GRANT. AND THE AMOUNT OF UP TO $1 MILLION, WHICH WOULD CARRY A 20% [00:05:07] MATCH FROM THE COUNTY, THE AWARD WAS MADE TO THE COUNTY OF 519,962. AND SO BETWEEN THESE TWO RESOLUTIONS, WE'RE GOING TO BE TRANSFERRING FUNDS OF 104,266 AND DOCKET 673 AND ON DOCKET 672, IT'LL END UP BEING A TRANSFER OF, 519 962. ANY QUESTIONS ON EITHER ONE OF THOSE TWO? HAVING NONE WILL TAKE THE VOTE ON 672. FIRST, ALL IN FAVOR, SAY AYE. AYE. ANY OPPOSE? PASSES UNANIMOUS. THE VOTE ON 673. ON FAVOR, SAY AYE. AYE. ANY OPPOSED? PASSES UNANIMOUSLY. TAKE A MOTION TO ADJOURN * This transcript was compiled from uncorrected Closed Captioning.